September 4th, 2008 by Sveden

Sigh. The Washington Ave Bridge is fuxored for the forseeable future. Avoid the bridge during 9-5 weekdays at all costs. At least the mopeds can’t get across the ped bridge now.

This is to update you on the latest developments
regarding the Washington Avenue Pedestrian Bridge.

Based on the recommendations of engineering consultants,
Hennepin County officials have closed the outside
portions of the Washington Avenue Pedestrian Bridge.
While other scenarios were considered as fencing was
constructed, county officials decided that use of the
pedestrian level must be limited until the deck is
strengthened. As of this afternoon, all pedestrians
and bicyclists must use the middle area inside the
covered enclosure.

To keep everyone safe, bicyclists should dismount and
walk their bikes across the bridge. The solution is
certainly not ideal and the congestion on the bridge
will be significant. Please continue to be considerate
and cooperative to other members of the University
community.

I understand the University community’s concern over
the bridge closure and the frustration with the changing
plans. I have stressed to Hennepin County officials the
vital role the bridge plays in the daily life of the
University and will continue to work closely with County
officials to protect the safety of our community and ensure
adequate pedestrian and bicycle movement across the
Mississippi River. Hennepin County is working to fast
track the project and work is expected to be completed
in the spring
. We will continue to provide updates
throughout the project.